Steps to Associate a Fixed Asset with a Project in MSD Axapta

Follow this procedure to associate a fixed asset record with a project:

1. Click Project > Projects.

2. Move to the project or subproject desired.

3. Click the Setup tab.

4. Click the Fixed asset field.

5. Select the desired fixed asset from the drop-down list of assets.

6. If you are in a parent project record and sub projects exist for the parent project, a Change of General Project Information form will open, asking which of the projects in the hierarchy you want to change. Select one of the following values:

• Only current project

• Edit only subprojects with the same value

• Edit all subprojects

7. Save the record. The asset is now associated with the project and its subprojects.