Follow this procedure to associate a fixed asset record with a project:
1. Click Project > Projects.
2. Move to the project or subproject desired.
3. Click the Setup tab.
4. Click the Fixed asset field.
5. Select the desired fixed asset from the drop-down list of assets.
6. If you are in a parent project record and sub projects exist for the parent project, a Change of General Project Information form will open, asking which of the projects in the hierarchy you want to change. Select one of the following values:
• Only current project
• Edit only subprojects with the same value
• Edit all subprojects
7. Save the record. The asset is now associated with the project and its subprojects.
1. Click Project > Projects.
2. Move to the project or subproject desired.
3. Click the Setup tab.
4. Click the Fixed asset field.
5. Select the desired fixed asset from the drop-down list of assets.
6. If you are in a parent project record and sub projects exist for the parent project, a Change of General Project Information form will open, asking which of the projects in the hierarchy you want to change. Select one of the following values:
• Only current project
• Edit only subprojects with the same value
• Edit all subprojects
7. Save the record. The asset is now associated with the project and its subprojects.