Skip to main content

Posts

Showing posts with the label sub project

Steps to Associate a Fixed Asset with a Project in MSD Axapta

Follow this procedure to associate a fixed asset record with a project: 1. Click Project > Projects. 2. Move to the project or subproject desired. 3. Click the Setup tab. 4. Click the Fixed asset field. 5. Select the desired fixed asset from the drop-down list of assets. 6. If you are in a parent project record and sub projects exist for the parent project, a Change of General Project Information form will open, asking which of the projects in the hierarchy you want to change. Select one of the following values: • Only current project • Edit only subprojects with the same value • Edit all subprojects 7. Save the record. The asset is now associated with the project and its subprojects.